Pledge amount for the new temple $1,479,250

Amount donated as of 2/16/2026 is $835,000

Temple construction update

Site plans, boundary surveys, and topographic surveys have been completed and formally submitted for zoning approval. The zoning hearing is scheduled for February 24, 2026.


Applications for fire inspection and final county inspections have been duly submitted. Upon completion and approval of these inspections, we will obtain the occupancy permit. Following receipt of the occupancy permit, we look forward to welcoming our congregation and the broader community to the new temple premises.

A temple building committee and an advisory committee of experienced professionals have been formed. A well-regarded local architect has been identified and engaged. The building committee is conducting a feasibility study to evaluate project components and associated costs, which will guide the phased development and construction plan. Based on the feasibility study, the temple construction phases with timelines will be finalized.